The journey from a cluttered workshop to a streamlined production floor often begins with a single, pivotal step: implementing SMED. This lean manufacturing technique, focused on reducing equipment changeover times, bridges the gap between theoretical efficiency and practical application.
Read on and explore a real-world SMED example that illustrates how theory translates into tangible improvements in manufacturing agility and productivity.
Before delving deeper into this pivotal efficiency-enhancing tool, it’s crucial to grasp the meaning behind the acronym SMED. Starting from the end, the “D” in SMED represents “dies” or a singular “die.” In manufacturing, a die is an essential tool that shapes and sizes the product, functioning akin to a stamp or an industrial version of a cookie-cutter.
Advancing to the “E,” it signifies the “exchange of dies.” Given that each die is tailored for producing specific product dimensions and shapes, different products necessitate different dies. Consequently, exchanging dies refers to the process of transitioning the production line from fabricating one product variant to another.
The initial letters, “SM,” denote “single-minute,” encapsulating the ideal timeframe for this transition — aiming for the exchange of dies to occur within a single minute. However, this concept can be expanded to signify a “single-digit minute exchange of dies,” implying the goal is to complete the die exchange in under ten minutes, thereby streamlining production processes and enhancing operational efficiency.
Related: SMED in Lean Manufacturing: What It is And How You Can Benefit From It

To fully grasp the potential of SMED, it’s beneficial to examine a practical example of its implementation. This segment outlines a straightforward and actionable guide for applying SMED principles effectively.
SMED has the capacity to revolutionize changeover processes for nearly all manufacturing entities engaged in changeovers. However, it’s essential to recognize that diving into SMED shouldn’t necessarily be the initial action step. Given the limited resources most companies face, prioritizing efforts where they can yield the most substantial returns is critical.
What should take precedence then? The cornerstone for most organizations should be to establish a robust understanding of where losses in productive time are occurring. This involves making informed decisions regarding improvement projects, grounded in solid, empirical data. To achieve this, instituting a mechanism for the diligent collection and analysis of manufacturing performance metrics is imperative.
A universally acknowledged benchmark for evaluating manufacturing efficiency is the measurement of OEE (Overall Equipment Effectiveness). This includes a further segmentation of OEE loss categories into the Six Big Losses, with an in-depth examination of OEE Availability losses segmented by Downtime Reason Codes. These codes are instrumental in tracking the duration of changeovers among other factors.
It’s advisable to gather manufacturing performance data over a minimum span of two weeks. This duration is essential to acquire a comprehensive understanding of where losses in productivity predominantly lie.
The foundational step in adopting the Single-Minute Exchange of Die (SMED) methodology involves pinpointing the most suitable pilot area for its implementation. This decision is critical as it sets the stage for the entire process, influencing the effectiveness and success of the SMED program. Here’s a structured approach to identifying this pivotal pilot area, focusing on specific criteria that ensure a balanced and impactful selection:
Involving a diverse group of employees in selecting the pilot area is key to securing support for the SMED initiative and ensuring a variety of perspectives contribute to the project. After choosing the target equipment through consensus, it’s essential to measure the current changeover time as a baseline. This measurement tracks the time from the last high-quality production at full speed to the start of the next, mindful of the “Hawthorne Effect” which suggests performance may temporarily improve under observation. Using pre-existing data when possible helps achieve a more accurate baseline, setting the stage for impactful improvements.
In this phase, the team collaboratively identifies every component involved in the changeover process. A highly effective method for achieving this is by recording the entire changeover process on video.
This allows the team to review the footage and compile a comprehensive list of components, detailing:
Practical Advice for Effective Identification:
This phase focuses on pinpointing activities within the changeover process that can be executed without disrupting ongoing operations, thus being classified as “external” activities (i.e., they can occur before or after the equipment is active).
The team should evaluate each activity with the question:
Should the answer be affirmative, the activity is designated as external and reassigned to either precede or follow the main changeover period.
Potential tasks suitable for this adjustment include:
The result of this stage should be a refined list of changeover activities, organized into three categories: External Activities (Before Changeover), Core Activities (During Changeover), and External Activities (After Changeover).
This phase entails a thorough review of the current changeover activities, aiming to reclassify as many internal activities (those that occur during downtime) as possible to external ones (those that can be done while operations continue).
The team should contemplate each internal activity with the mindset:
Such deliberation will generate a roster of activities ripe for reclassification. These should then be ranked based on potential impact, focusing initially on those with the most favorable cost-benefit ratio. This involves assessing:
With priorities set, efforts can shift towards implementing these modifications
Techniques for transitioning internal to external activities include:
The outcome of this step should be an evolved list of changeover activities, characterized by a reduced count of internal activities and an expanded suite of external ones, thereby streamlining the overall process.
At this stage, the focus shifts to the refinement and optimization of the remaining changeover activities. The objective is to make these processes more efficient, aiming for completion in the shortest possible time. Priority is placed on internal activities, as refining these directly contributes to the overarching goal of reducing changeover durations.
For each activity, the team examines two key questions:
A straightforward cost/benefit analysis continues to guide the prioritization of improvements, similar to the approach in previous steps.
Methods for enhancing efficiency include:
The result of this step is a comprehensive set of streamlined work instructions, leading to a significantly improved changeover process.
Now that you know more about SMED Example, why not check out our other blog posts? It’s full of useful articles, professional advice, and updates on the latest trends that can help keep your operations up to date. Take a look and find out more about what’s happening in your industry. Read More
Learn more about how our product, Smart Factory Suite, can drive productivity and overall equipment effectiveness (OEE) across your manufacturing floor. Schedule a meeting with a member of the Shoplogix team to learn more about our solutions and align them with your manufacturing data and technology needs. Request Demo